Research · Analysis · Editing · Publication Support · Gwalior, M.P.
+91 70009 37390 · info.shodhyantri@gmail.com · Admin Login
Shodhyantri Engineering Services - Research. Precision. Perfection.
Home › Our Work

Time–Cost Trade-off Analysis

Crashing, resource optimisation and the schedule compression that actually pays.

Project management

Smart planning, better results

Every project can be finished faster by spending more. The interesting question is where that stops being true — the duration at which the money saved on overheads no longer covers the money spent on acceleration.

The analysis on the poster is the classic one, worked through properly. Eight activities from excavation to MEP works, each with a normal duration and cost and a crashed duration and cost, giving a cost slope in rupees per week saved. Direct cost rises as duration falls; indirect cost falls; the total cost curve is the sum, and it has a minimum. In the worked example that minimum sits at twenty-four weeks, four weeks below the normal schedule, at a total of ₹52.80 lakh — an 8.7 per cent saving.

The reason the method matters is that intuition gets it wrong in both directions. Managers either refuse to crash at all, and pay indirect costs for longer than they need to, or they crash everything, and pay a fortune to compress activities that were never on the critical path and so saved no time at all.

That second error is the common one. Crashing an activity with float changes nothing about the project duration and costs real money. The whole discipline of the method is: find the critical path, crash the cheapest critical activity by one unit, recompute the path because it may have changed, and repeat until the total cost starts rising.

Time–Cost Trade-off Analysis
Time–Cost Trade-off Analysis — optimising duration, minimising total cost.
What is on the poster

What the analysis involves

From the activity list to a defended optimum duration.

  • Work breakdown structure and activity definition
  • Activity sequencing with realistic dependencies and lags
  • Normal and crashed duration and cost estimation for every activity
  • Cost slope calculation and ranking of crashing candidates
  • Network modelling with critical path and float identification
  • Step-by-step crashing with the critical path recomputed at each step
  • Indirect cost modelling — supervision, equipment hire, site overheads, finance
  • Total cost curve construction and optimum point identification
  • Resource levelling and allocation across compressed schedules
  • Gantt and schedule compression comparison, before and after
  • What-if scenario analysis on productivity, weather and material availability
  • Primavera P6 and MS Project models handed over so the plan stays usable

Where the numbers in a crashing study come from

The weak point of most time–cost studies is the crash cost estimate. Normal durations and costs are usually available from schedules of rates or from the contractor's own data. Crash costs — what it actually costs to do the same activity in three weeks instead of four — are far softer, because they depend on overtime rates, additional plant, crew size limits and productivity loss from crowding.

An honest study states the basis of each crash estimate and acknowledges the productivity penalty. Doubling the crew rarely halves the duration; congestion, supervision limits and learning all bite. A study that assumes linear scaling will overstate what crashing can achieve, and a practitioner reading it will notice immediately.

The same care applies to indirect cost. It is often taken as a flat weekly figure, which is a reasonable simplification for site overheads but not for finance charges or for penalty and bonus clauses that step at specific dates. Where the contract has a liquidated damages provision, that belongs in the model, and it usually shifts the optimum considerably.

Isometric 3D bar chart with a trend line
Direct, indirect and total cost plotted against duration, with the optimum marked.
How the work runs

The eight-step workflow

1

Collect project data

Activity list, durations, costs, resources and the contract terms that affect time — penalties, bonuses, milestone dates.

2

Sequence the activities

Dependencies and lags that reflect how the work is really built, not a tidy chain.

3

Estimate duration and cost

Normal and crashed values for each activity, with the basis of the crash estimate recorded.

4

Model the network

Critical path, floats and the activities where compression can actually buy time.

5

Crash step by step

Cheapest critical activity first, recomputing the path at every step because it moves.

6

Find and report the optimum

The total cost curve, the minimum, the saving, and a recommendation with its assumptions stated.

Beyond the textbook curve

Classical crashing assumes deterministic durations, which no site has. Where the schedule risk matters, the stronger analysis is stochastic: assign a distribution to each activity duration, run a Monte Carlo simulation, and report the probability of finishing by a given date rather than a single number. A twenty-four-week plan with a forty per cent chance of being met is a different proposition from one with an eighty-five per cent chance.

Resource constraints change the answer too. A schedule that is optimal on paper may be impossible if it needs two tower cranes on a site that has one. Resource-constrained scheduling and levelling are part of the same study, and skipping them is how a thesis produces a plan that a site engineer would laugh at.

Where a genuine research contribution is wanted rather than an application, the usual route is multi-objective: time, cost and one more objective such as quality, safety or carbon, solved with a genetic algorithm to produce a trade-off front instead of a single optimum. We build those too, and the optimisation page on this site covers how they are assessed.

What it costs. Price depends on scope — the size of the dataset, the number of chapters, the journal you are aiming at. Send us the actual material on WhatsApp and you will get a figure for your work, not a price list.
What you receive
Work breakdown structure and activity list
Duration and cost table with crash estimates and their basis
Network diagram with critical path and floats
Step-by-step crashing table
Direct, indirect and total cost curves with the optimum marked
Compressed Gantt chart against the original
Resource histograms before and after levelling
Primavera or MS Project file, plus the written analysis
Primavera P6Microsoft ProjectAutodesk RevitNavisworksExcelMATLABPython
Questions

About this service

Where do I get crash cost data if I have no site access?

Published schedules of rates, contractor interviews, and academic case data are the usual sources. Whichever you use, state it, and treat the crash estimates as the study's main uncertainty — then test how far the optimum moves if they are twenty per cent out.

Should I crash activities that are not on the critical path?

No. Compressing an activity with float spends money and saves no time. The only exception is when the float is small enough that the activity is about to become critical, which is why the path is recomputed after every crashing step.

Can this be done with a genetic algorithm instead?

Yes, and for large networks or three or more objectives it is the better route — you get a trade-off front rather than a single point. NSGA-II is the usual choice for time and cost; NSGA-III once quality, safety or carbon are added.

Do you work with Primavera P6 or only MS Project?

Both. We hand over the native file so your plan stays editable, along with exports in PDF and Excel for anyone who does not have the software.

Related work

Other things we are asked for alongside this

Engineering Research Excellence

Engineering Research Excellence

Conceptual design, CAD, FEA, thermal and fluid analysis, optimisation and validation.

Read more
NSGA-II and NSGA-III Optimisation

NSGA-II and NSGA-III Optimisation

Multi-objective and many-objective optimisation with Pareto fronts and reference points.

Read more
Sustainable Concrete Mix Design

Sustainable Concrete Mix Design

Waste material replacement, experimental testing and performance evaluation for M30 and beyond.

Read more
Free first consultation

Tell us what you are stuck on.

Send your topic, your dataset or one draft chapter. We will tell you honestly what it needs — before you pay anything. The first consultation is free.

Chat on WhatsApp Call